top of page

Business Disputes, Debt Recovery

​

Using the Security of Payment Regime to Get Paid – Short Cut for Subcontractors
​

There are payment requirements in the building and construction industry that principals, head contractors, subcontractors and suppliers must follow. These are regulated by the Building and Construction Industry Security of Payment Act 1999 (the Act).

All contractors providing goods or services as part of construction work have the right to receive ‘progress payments’ for work delivered.

​

What To Do If You Have Not Been Paid? 

​

There are two steps to take if you have not received a payment schedule within the required number of business days after making a claim, or you have not been paid by the due date.

Step 1: Ensure you have made a claim for payment.

Step 2: Apply for adjudication.

Entitlement to Progress Payments

Contractors have a right to progress payments whether a contract is verbal, written or absent, and even if a contract states the contractor cannot claim progress payments. Unless otherwise stated in the contract, progress payment claims can only be made once per month.

The progress payment amount is calculated based on:

• The terms of the contract, or

• The value of the work carried out (if not specified in the contract terms).

Disputes

If there is a dispute over the amount of a progress payment owed, contractors can have an arbitrator determine the dispute under certain circumstances.

Summary of Key Deadlines

The tables below show the key deadlines that are set out in the Act for:

• Making a payment claim

• Responding to a payment claim with a payment schedule

• Applying for adjudication, and

• Making a payment withholding request.

Note your contract could specify shorter deadlines.

Payment Following a Payment Claim

After a payment claim is made for the construction work and services performed, the following due dates for payment apply.

Payment Claim Key Deadlines/Due Dates*

Payment by Principal to Head Contractor 15 days after claim is made

Payment by Head Contractor to Subcontractor (Non-Residential) 30 days after claim is made

Payment by Head Contractor to Subcontractor (Residential) 10 days after claim is made

*business days.

Giving a Payment Schedule

A payment schedule may be given if the person responding to a claimant does not intend to pay the total amount claimed and states why. The payment schedule is only valid within the set periods outlined below.

Payment Schedule Key Deadlines/Due Dates*

After claim is made before due date has expired 10 days after claim is made

After claim is made after due date has expired 5 days after receiving notice of intention to apply for adjudication

*business days.

Adjudication Process

Only a claimant can start adjudication and they must apply within set periods. The key dates for the claimant, respondent and adjudicator in this process are listed below.

Adjudication Application Key Deadlines/Due Dates*

Notice of intention to apply for adjudication 20 days after due date has passed

Claimant receives payment schedule, does not dispute schedule but respondent fails to pay by due date 20 days to lodge application

Claimant receives payment schedule, schedule amount is less than claim amount 10 days to lodge application

No payment schedule received, due date has passed, respondent given notice of intention to apply for adjudication, respondent given further 5 days to give payment schedule 10 days to lodge from last day of the 5 day notice period

Adjudicator acceptance Should be within 4 days of adjudication application, otherwise claimant can make new application

New adjudication application Within 5 days of becoming entitled to lodge new application

Adjudication response Due 5 days after receiving adjudication application from claimant, or 2 days after receiving adjudicator acceptance

Adjudicator’s decision Due within 10 days of adjudicator acceptance

Payment of adjudication amount 5 days after release of adjudicator decision

*business days.

Payment Withhold Request

A claimant who has made an adjudication application can serve a payment withholding request. This directs a principal contractor (above the respondent in a chain of contracts) to hold back a respondent’s payment, so there is enough money to cover a claim.

Payment Withholding Request Key Deadlines/Due Dates*

Principal contract served with payment withholding request. If person no longer a principal contractor 10 days to give notice to claimant

Claimant must serve adjudication determination on principal contractor Within 5 days of receiving determination

If adjudication application is withdrawn, claimant must notify principal contractor Within 5 days of the application being withdrawn

Claimant must serve notice of claim to principal contractor under Contractors Debt Act 1997 Within 20 days of serving adjudication determination on them

*business days.

Original composition by Sean K. Devine (various sources)

Statutory Demands – Act quickly or risk you Company being wound up
​

If you are a company director, your company may be served with a Statutory Demand under Section 459E of the Corporations Act.

The section is meant to be a pre-cursor to establishing that your company is insolvent and should be wound up – partly on public policy grounds. The ulterior motive of course can really be a way of short-cutting bringing a debt due from the company to your immediate notice.

While it is an illegitimate purpose to use the winding up Courts to recover debts – the practical reality is – if you fail to comply with the Statutory Demand, your company may be deemed to be insolvent.  Presenting the proper evidence to prove otherwise can be expensive and difficult especially for smaller businesses that always operate close to the margins.

The Statutory Demand is usually served on the registered office of the company. Once served with the Statutory Demand, you are required to comply with the demand to pay the money claimed within 21 days of receipt of the Statutory Demand.

Failure to comply with the time limit may result in winding up proceedings being initiated by the creditor against your company.

A High Court in this case clearly confirmed that the time limit of 21 days could not be extended by the parties to the proceedings. If you do not pay the outstanding sum within 21 days, then there is a presumption that your company is insolvent.

The only basis that you can seek to set aside a Statutory Demand is –

  1. if there is a genuine dispute;

  2. if you have an offsetting claim;

  3. the Statutory Demand is defective; or

  4. any other reason the court can be convinced of to set it aside.

Where you do not have grounds to have the Statutory Demand set aside, then time is of the essence in that you will have to pay the debt within 21 days.

Should you require further information on Statutory Demands, please do not hesitate to contact Sean Devine   sean@devinehoangpartners.comau or Free Call 1300 59 33 98

​

If you are a company director, your company may be served with a Statutory Demand under Section 459E of the Corporations Act.

The section is meant to be a pre-cursor to establishing that your company is insolvent and should be wound up – partly on public policy grounds. The ulterior motive of course can really be a way of short-cutting bringing a debt due from the company to your immediate notice.

While it is an illegitimate purpose to use the winding up Courts to recover debts – the practical reality is – if you fail to comply with the Statutory Demand, your company may be deemed to be insolvent.  Presenting the proper evidence to prove otherwise can be expensive and difficult especially for smaller businesses that always operate close to the margins.

The Statutory Demand is usually served on the registered office of the company. Once served with the Statutory Demand, you are required to comply with the demand to pay the money claimed within 21 days of receipt of the Statutory Demand.

Failure to comply with the time limit may result in winding up proceedings being initiated by the creditor against your company.

A High Court in this case clearly confirmed that the time limit of 21 days could not be extended by the parties to the proceedings. If you do not pay the outstanding sum within 21 days, then there is a presumption that your company is insolvent.

The only basis that you can seek to set aside a Statutory Demand is –

  1. if there is a genuine dispute;

  2. if you have an offsetting claim;

  3. the Statutory Demand is defective; or

  4. any other reason the court can be convinced of to set it aside.

Where you do not have grounds to have the Statutory Demand set aside, then time is of the essence in that you will have to pay the debt within 21 days.

Should you require further information on Statutory Demands, please do not hesitate to contact Sean Devine   sean@devinehoangpartners.comau or Free Call 1300 59 33 98

bottom of page